Anders J. Lenborg
Hi and welcome to Cloudberry Clean Energy. The first half-year report.
My name is Anna Lenborg and I'm joined here by our CFO, Ole-Kristofer Bragnes.
We have a presentation for you that we would like to go through.
And please also use the Q&A button and send us questions. And we will try to answer as many of the questions as possible after the presentation.
Before diving into the details, let's have a look at the agenda.
I will go through the highlights and then Ole-Kristofer will take you through the key financials, and I will finish up with some comments to the market.
Uh, and here you see our hydropower intake on our Sørfjord project on the right-hand side. It has been a busy quarter for Cloudberry. We have had many basic quarters, but this has been a very interesting quarter where we have partnered up with Swiss Life, creating one of the top three small-scale hydropower platforms in the Nordics. Our cooperation with Swiss Life goes back to 2020. And we have constantly developed our partnership and our portfolio.
And with this new merger of our resources, we create a platform that can cover the full lifecycle of our hydropower projects. So very pleased to see that and very happy to come back to that later in the presentation.
That has been, or is, a game-changer for the Cloudberry Hydro platform.
In addition to that, we have formed a partnership and also entered into a cooperation with Ox2 on our dualling project in AC3. So, uh, that is also a new constellation for us, and we are looking forward to the cooperation with OX2 on the wind side. And another highlight for the quarter is our FID on the Nelson Bess project. Uh, it's a project that we have worked on over time with our partner in the utility of Oslo. And we are happy to have taken the FID on our first, uh, BESS project. And last but not least, we are always following up on our production assets and making sure that they produce as efficiently as possible. As good as possible.
And happy to say that we have all turbines back in service. On the, on the, um, wind farm you see here on the, on the right hand side that our production, um, has increased throughout the years, almost doubling in the last quarter, uh, and also the installed capacity has increased. It looks like a small decrease on the capacity side, but that's due to the Fortum transaction.
But if you also add the power plants under construction, there will be an increase in installed capacity. Ole-Kristofer will come back to the numbers in more detail. But we are very happy to see that we have realized the power price that is twice the system price in the Nordics.
So, uh, it shows that our strategy when it comes to diversifying our portfolio across different price areas and technologies and staying merchant is, uh, an attractive one.
But, um, let's take one step back and just spend a couple of minutes on who we are. Um, the Cloudberry platform. Uh, we have created a profitable Nordic IP over the last few years. Uh, we are covering our project from a very early greenfield phase to when they are in production and under operations. To have a platform covering the full lifecycle of our projects is important for us.
And uh, this develop, own and operate strategy has also given us a lot of flexibility, which, together with the portfolio we have now for different technologies with different production profiles, is advantageous. We are in three different countries with different regulatory regimes.
Eight different price areas where we have the vast majority of our projects in the southern price areas of Norway and the southern price areas of Sweden, and in addition, one in Denmark. As you can see here on the map, we have some development projects and construction projects in the north of Norway, and these are some of the projects that have recently been added to our portfolio. But we will keep focusing on the attractive southern price areas, and we will then continue also to develop the projects in the South.
So this combination of different countries, price areas, technologies, and projects in different phases gives us fantastic flexibility. And I think the flexibility of Cloudberry, the flexibility in the platform and in the portfolio, has been super important for delivering good results throughout a difficult market. And it's also important to note that our backlog with exclusive projects is something that we develop in-house from greenfield. And the pipeline is something that we use to make the best possible mix of projects and technologies, leveraging our network and through M&A activities. So, we have a combination of in-house developed projects, but we also utilize the market where we see the best opportunities. So so that's Cloudberry in short, a Nordic profitable IP platform with great flexibility. And here you see our production profile.
Um, our production portfolio has increased over the years. And as you can see, we have also focused on diversifying it and expanding it further.
And as you see here on the right-hand side, we will keep diversifying it by now also including batteries and the best projects in the portfolio. We are happy to see that after five years, we have managed to pass 1000 GWh, or one terawatt hour, in production. And here you have the breakdown of our production portfolio on the left-hand side. As you can see, there's also an increase in production when we consider the projects under construction. But just as important is the right-hand side where you see our backlog and permitted projects. And we always focus on adding new projects to the backlog and looking at attractive possibilities in the pipeline. To always make sure that we build a portfolio that is diversified and also with an attractive production profile throughout the year, so we can deliver stable production. We have also added a slide to the presentation on the future transaction. As I said, we are very happy to create a new leading hydropower platform in the Nordics.
Top three. A new project in our backlog, but it also adds a lot of knowledge, experience, and capabilities in developing the project from early phase greenfield projects until they are in operation.
And we have them under our management.
And we have touched upon the hydro expansion.
We have also talked about the Dinnington project. Also happy to see new partnerships forming on the wind side in Sweden. Uh, as many remember, we entered into a partnership with Holmen, one of the larger owners of land in Sweden, but have now also entered into a partnership with Sverre Skoog, one of the largest landowners in Europe and the largest forest owner in Sweden.
And we have a 100 megawatt project there to start with, and we will add new projects to that portfolio. On the Danish expansion, we have touched upon that earlier, but we have also now seen that we have managed to get a very positive overall valuation on our farm.
The sale of Hywind farm in Norway was conducted with 17 co-owners, similar to the approach we took during the acquisition in Denmark. On the future, going towards 2030, we will continue to focus on profitability over growth. Uh, that has been our focus over the last couple of years, and it will continue. Uh, we have seen that some of the projects will not meet our requirements. Then we take a step back, we redesign, and we use more time on it instead of trying to push things through. Uh, because we also have a lot of other projects in our portfolio that are meeting our return requirements. So we will continue to focus on profitability over growth. And we have always focused on being very well-financed, maintaining a strong balance sheet, and that will also continue in the future. And of course, to see the team delivering on these projects, on the different technologies and redesigns, and all the things we work with now is very satisfying and we are very happy with how we have executed on these projects over the last quarter. Yeah, on the ESG side.
I think the most important is that we have had no recordable incidents or damages in the second quarter. Then I give the word to Ole-Kristofer, who will take you through the key financials. And I will come back at the end of the presentation.
Thank you.